2009 ROAD CONSTRUCTION PROGRAM
& SCHEDULE OF WORK
(last updated: Sept 24, 2009)
The Public Works Department has listed the following streets to be resurfaced during the 2009 construction season:
SALEM STREET ( Lara Lane to Summer Street)
June 10-11th |
Mill off top surface of pavement(expect delays) |
Completed |
Week of June 15th |
Install new binder asphalt (expect detours) |
Completed |
Week of July 6th |
Raise castings to grade (expect delays) |
Completed |
July 14th |
Stripe road |
Completed |
July 27th-Aug. 14th |
Install new granite curbing (expect delays) |
Completed |
Sept. 23rd - Sept. 29th |
Loam and seed |
On schedule |
Sept. 17th - Sept. 22nd |
Repair sidewalk and driveway aprons as necessary |
Completed |
During construction there will be DELAYS and DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.
SUMMER STREET(#164 Summer to Summer Street School)
June 10th-11th |
Mill off top surface of pavement(expect delays) |
Completed |
June 15th |
Adjustment of castings |
Completed |
Week of June 15th |
Install finish pavement(expect delays) |
Completed |
July 14th |
Stripe Road |
Completed |
HERITAGE LANE(#26 Heritage Lane to Windsor Road)
June 4th -9th |
Remove asphalt curbing |
Completed |
June 10th-11th |
Mill off top surface of pavement(expect delays) |
Completed |
June 15th-16th |
Cut and remove section of roadway(expect delays) |
Completed |
June 17th |
Install new binder asphalt(expect delays) |
Completed |
June 18th-June 26th |
Install granite curbing and handi-cap ramps |
Completed |
June 30th |
Install new asphalt curbing(expect delays) |
Completed |
July 13th-July 17th |
Loam and seed |
Completed |
July 10th |
Install new finish asphalt(expect delays) |
Completed |
July 20th-July 21st |
Repair driveway aprons as necessary |
Completed |
During construction there will be DELAYS and DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.
MAIN STREET ( @ S. COMMON STREET)
June 10th-June 11th |
Mill off top surface of pavement(expect delays) |
Completed |
June 15th-June 19th |
Install granite curbing and handi-cap ramps(expect delays) |
Completed |
June 29th |
Raise castings for finish pavement |
Completed |
July 1st -July 2nd |
Loam and seed |
Completed |
July 10th |
Install new finish pavement(expect delays) |
Completed |
July 14th |
Stripe road |
Completed |
|